A MILP model for an extended version of the Flexible Job Shop Problem

arXiv 1401.3654 ↗First posted 15 Jan 2014cs.DS cs.DMcited by 5

Not on the map. Why?

Abstract (arXiv)

A MILP model for an extended version of the Flexible Job Shop Scheduling problem is proposed. The extension allows the precedences between operations of a job to be given by an arbitrary directed acyclic graph rather than a linear order. The goal is the minimization of the makespan. Theoretical and practical advantages of the proposed model are discussed. Numerical experiments show the performance of a commercial exact solver when applied to the proposed model. The new model is also compared with a simple extension of the model described by "Ozg"uven, "Ozbakir, and Yavuz (Mathematical models for job-shop scheduling problems with routing and process plan flexibility, Applied Mathematical Modelling, 34:1539--1548, 2010), using instances from the literature and instances inspired by real data from the printing industry.

Key facts. Cited by 5 papers in the map (data through 14 Oct 2026). First posted on arXiv 15 Jan 2014.

Builds on

No reference list yet.

Built on by

Cited by year (2026 to 14 Oct)

Citing papers per year: 2022: 1; 2023: 1; 2024: 0; 2025: 2; 2026: 1.

5 papers.