Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags
Not on the map. Why?
Abstract (arXiv)
This study investigates scheduling strategies for the stochastic resource-constrained project scheduling problem with maximal time lags (SRCPSP/max)). Recent advances in Constraint Programming (CP) and Temporal Networks have reinvoked interest in evaluating the advantages and drawbacks of various proactive and reactive scheduling methods. First, we present a new, CP-based fully proactive method. Second, we show how a reactive approach can be constructed using an online rescheduling procedure. A third contribution is based on partial order schedules and uses Simple Temporal Networks with Uncertainty (STNUs). Our statistical analysis shows that the STNU-based algorithm performs best in terms of solution quality, while also showing good relative offline and online computation time.
Key facts. Cited by 1 paper in the map (data through 14 Oct 2026). Builds on 1 of its 28 references that are in the map. First posted on arXiv 13 Sep 2024.
Builds on
1 of 28 references.
References · 1
Built on by
Citing papers per year: 2025: 1.
1 paper.