Answer-Set Programming for Lexicographical Makespan Optimisation in Parallel Machine Scheduling

arXiv 2212.09077 ↗First posted 18 Dec 2022cs.AIcited by 3

Not on the map. Why?

Abstract (arXiv)

We deal with a challenging scheduling problem on parallel machines with sequence-dependent setup times and release dates from a real-world application of semiconductor work-shop production. There, jobs can only be processed by dedicated machines, thus few machines can determine the makespan almost regardless of how jobs are scheduled on the remaining ones. This causes problems when machines fail and jobs need to be rescheduled. Instead of optimising only the makespan, we put the individual machine spans in non-ascending order and lexicographically minimise the resulting tuples. This achieves that all machines complete as early as possible and increases the robustness of the schedule. We study the application of Answer-Set Programming (ASP) to solve this problem. While ASP eases modelling, the combination of timing constraints and the considered objective function challenges current solving technology. The former issue is addressed by using an extension of ASP by difference logic. For the latter, we devise different algorithms that use multi-shot solving. To tackle industrial-sized instances, we study different approximations and heuristics. Our experimental results show that ASP is indeed a promising KRR paradigm for this problem and is competitive with state-of-the-art CP and MIP solvers. Under consideration in Theory and Practice of Logic Programming (TPLP).

Key facts. Cited by 3 papers in the map (data through 7 Oct 2026). Builds on 4 of its 38 references that are in the map. First posted on arXiv 18 Dec 2022.

Builds on

4 of 38 references.

References · 4

  1. 2017Multi-shot ASP solving with clingocited by 115
  2. 2019ASP-Core-2 Input Language Formatcited by 77
  3. 2017Clingo goes Linear Constraints over Reals and Integerscited by 18
  4. 2018Exact Lexicographic Scheduling and Approximate Reschedulingcited by 1

Built on by

Cited by year (2026 to 7 Oct)

Citing papers per year: 2023: 1; 2024: 0; 2025: 1; 2026: 1.

3 papers.