A faster exact method for solving the robust multi-mode resource-constrained project scheduling problem

arXiv 2203.06983 ↗First posted 14 Mar 2022math.OC cs.DMcited by 1

Not on the map. Why?

Abstract (arXiv)

This paper presents a mixed-integer linear programming formulation for the multi-mode resource-constrained project scheduling problem with uncertain activity durations. We consider a two-stage robust optimisation approach and find solutions that minimise the worst-case project makespan, whilst assuming that activity durations lie in a budgeted uncertainty set. Computational experiments show that this easy-to-implement formulation is many times faster than the current state-of-the-art solution approach for this problem, whilst solving over 40% more instances to optimality over the same benchmarking set.

Key facts. Cited by 1 paper in the map (data through 7 Oct 2026). First posted on arXiv 14 Mar 2022.

Builds on

No reference list yet.

Built on by

Cited by year (2026 to 7 Oct)

Citing papers per year: 2026: 1.

1 paper.