In order to coordinate the scheduling problem between an isolated microgrid (IMG) and electric vehicle battery swapping stations (BSSs) in multi-stakeholder scenarios, a new bi-level optimal scheduling model is proposed for promoting the participation of BSSs in regulating the IMG economic operation. In this model, the upper-level sub-problem is formulated to minimize the IMG net costs, while the lower-level aims to maximize the profits of the BSS under real-time pricing environments determined by demand responses in the upper-level decision. To solve the model, a hybrid algorithm, called JAYA-BBA, is put forward by combining a real/integer-coded JAYA algorithm and the branch and bound algorithm (BBA), in which the JAYA and BBA are respectively employed to address the upper- and lower- level sub-problems, and the bi-level model is eventually solved through alternate iterations between the two levels. The simulation results on a microgrid test system verify the effectiveness and superiority of the presented approach.

Key facts. Cited by 2 papers in the map (data through 14 Oct 2026). First posted on arXiv 26 Sep 2018.

Builds on

No reference list yet.

Built on by

Cited by year

Citing papers per year: 2022: 2.